Fakta om udbudet
Udbyder
DONG Energy Thermal Power A/S
Vindere
(27.06.2016)
Heat wärmetechnische Anlagen Ges.m.b.H
Siegfried Marcus-Straße 9
2362 Biedermannsdorf
HCV MR Station M-01 MR Station
DONG Energy Thermal Power A/S
Contract award notice – utilities
Results of the procurement procedure
Supplies
Directive 2014/25/EU
Section I: Contracting entity
27 44 64 69
Kraftværksvej 53
Fredericia
7000
Denmark
Contact person: Jens Vollertzen
Telephone: +45 99558771
E-mail: jenvo@dongenergy.dk
NUTS code: DK042
Internet address(es):
Main address: http://www.dongenergy.com
Section II: Object
HCV MR Station M-01 MR Station.
The Municipality of Copenhagen and CPH City and Port has decided to establish homes and offices in the former industrial area between HC Ørsted Power Plant and the harbour at Enghave Brygge. In this context, the transmission line from Amager to HC Ørstedsværket shall be redirected.
This contract notice includes the project to plan, design and build a new MR station that can be connected to the existing plant at HC Ørsted Power Plant and Energinet.dk's re-engineered gas pipeline. The new MR Station shall be delivered as a turnkey delivery.
H C Ørsted Værket, Tømmergravsgade 4, 2450 Copenhagen, Denmark.
The MR station is supplied with 55 bar gas from a transmission line. The gas is to be reduced in pressure in the MR-station and supplied to HCV on 2 pressure levels:
1. Approximately 4 bar gas with a total maximal nominal consumption of approximately 55 000 Nm3/h;
2. Approximately 24 bar gas with a total maximal nominal consumption of approximately 11 000 Nm3/h;
The turnkey contract contains as a minimum — but not limited to — the following:
— Design / detailed design of all deliveries;
— Delivery of documentation and materials for the purpose of regulatory approval (technical specifications regarding gas, environmental and construction-related regulatory procedures);
— Proof of delivery;
— Compliance with technical specifications from DONG Energy;
— Information on dimensions, weight, etc. to be used for foundations;
— Architectural project(s), including design drawings, descriptions, as-built drawings, calculations, etc.;
— Establishment of structures.
Section IV: Procedure
Section V: Award of contract
HCV MR Station M-01 MR Station
14855209
Siegfried Marcus-Straße 9
Biedermannsdorf
2362
Austria
E-mail: heat@heatgroup.at
NUTS code: AT130
Internet address:www.heatgroup.at
Section VI: Complementary information
Dahlerups Pakhus, Langelinie Allé 17
Copenhagen Ø
2100
Denmark
Telephone: +45 35291000
E-mail: klfu@erst.dk
Internet address:www.klfu.dk
Precise information on deadline(s) for lodging appeals the deadlines are provided in Danish act no 492 of 12.5.2010 on enforcement of the public procurement rules, etc. (only available in Danish).
Appeals of the tender procedure shall be lodged to Klagenævnet for Udbud within 45 calendar days after the contracting entity has published the contract award notice in The Official Journal of the European Union. The deadline is calculated from the day after the day when the contract award notice is published.
The complainant must notify the contracting entity in writing of the filling of a complaint with Klagenævnet for Udbud (the Review body) at the latest when he files the complaint with Klagenævnet for Udbud, and the notification must contain information about whether the complaint is filed in the standstill period. If the complaint is not filed in the standstill period, the complaint must also state if it is requested that the complaint be granted suspensory effect.
Carl Jacobsensvej 35
Valby
2500
Denmark
Telephone: +45 41715000
E-mail: kfst@kfst.dk
Internet address:www.kfst.dk