Fakta om udbudet
Bestilling af materiale
http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=149704&B=ENERGINET
Anmodning om deltagelse
Addresse
https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
Udbyder
Energinet.dk
Vindere
(31.03.2016)
Schlumberger Danmark A/S
Tværkaj 2
6700 Esbjerg
Frame Agreement for the supply of onshore services related to wells on natural gas aquifer storage
Energinet.dk
Contract notice – utilities
Services
Section I: Contracting entity
Energinet.dk
28980671
Tonne Kjærsvej 65
For the attention of: Indkøbs Afdelingen
7000 Fredericia
DENMARK
Telephone: +45 70102244
E-mail: indkob@energinet.dk
Internet address(es):
General address of the contracting entity: http://www.energinet.dk
Address of the buyer profile: http://eu.eu-supply.com/ctm/Supplier/CompanyInformation/Index/228008
Electronic access to information: http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=149704&B=ENERGINET
Further information can be obtained from: The above mentioned contact point(s)
Specifications and additional documents (including documents for a dynamic purchasing system) can be obtained from: The above mentioned contact point(s)
Tenders or requests to participate must be sent to: The above mentioned contact point(s)
Electricity
Section II: Object of the contract
Service category No 27: Other services
Main site or location of works, place of delivery or of performance: Merløsevej 1C, 4296 Nyrup.
NUTS code DK02
Number of participants to the framework agreement envisaged: 1
Duration of the framework agreement
Duration in years: 3Estimated total value of purchases for the entire duration of the framework agreement
Estimated value excluding VAT: 4 000 000 DKK1. Pulsed neutron logging of gas and sand in gas storage wells, including interpretation of the logs and reporting of results.
2. Wireline, pumping and coil tubing jobs, well consulting services (engineering) and emergency preparedness.
Energinet.dk intends to award the framework agreement to one supplier per partial agreement. The tenderer have to indicate in the pre-qualification if they want to qualify for partial agreement 1, 2 or both 1 and 2. The gas is stored in a sandstone formation named Gassum at a depth of about 1 500 m. The Gassum Formation is subdivided in 6 zones separated by thin clay-stone stringers. The services will include the necessary activities for Energinet.dk to be able to comply with their obligations due to legislation as well as the necessary and usual activities of services related to well maintenance on natural gas storage.
76000000, 76100000, 76510000, 76300000, 76440000, 76443000, 76533000
Tenders may be submitted for one or more lots
Description of these options: Extension of the contract for 2 X 12 month.
Provisional timetable for recourse to these options:
in months: 24 (from the award of the contract)
Information about lots
Lot No: 1 Lot title: Pulsed neutron logging including data interpretationThe number of wells to be logged varies from year to year, but the average number is expected to be 6 wells a year. The interval to be logged is from a few meters above the top of upper sand layer in the caprock to total depth of the reservoir.
During the pulsed neutron logging the tubing head pressure/temperature and the pressure/temperature at top of perforations shall be measured and reported.
The interpretation of the logs must determine the gas saturation as a function of depth. It is important that the new logs can be compared directly with previous logs as the main objective is to detect changes which could indicate gas in the caprock. Energinet.dk will supply the data from the open hole logs and the previous pulsed neutron logs to enable the service company to plot the new log on top of the old logs.
76000000, 76100000, 76300000, 76440000, 76443000, 76510000, 76533000
The equipment and personnel provided shall be suitable to perform the activities necessary and usual for natural gas storage in standard 5000 psi wells, including:
— Electric Line (up to 5/16” mono-conductor) cased whole Logging Ser-vices.
— General Slick line and Braided Line Intervention work.
— Heavy Duty Braided Line Fishing Services.
— Coil Tubing Service.
— Pumping Services.
— Technical assistance on office duties: the service company shall when required provide onshore project management, well design engineer and engineering support. This work shall be to assist Energinet.dk's operation planning, well design, intervention, technology qualification and/or studies.
— Emergency preparedness: Annual assessment and discussion of the contingency plan of Energinet.dk, as well as a commitment to act on incidents (engineering, supervision and equipment) and prospective completing annual training exercise.
76000000, 76100000, 76510000, 76300000, 76440000, 76443000, 76533000
Section III: Legal, economic, financial and technical information
A template regarding the above mentioned can be downloaded at www.energinet.dk/tenders or from EU supply.
If suppliers have joint forces (i.e. joint ventures, consortia, ect.) the declaration must be provided for each individual supplier. The application must also clearlystate the constellation which applies for pre-qualification and include a declaration whereby all participants of the consortium have assumed direct, unlimited and joint and several liability and whereby one participant of the consortium has been duly authorized to unrestrictedly bind the other participants of the consortium by such participant's sole signature.
The applicant's annual report and key figures will be subject to evaluation of whether the applicant undoubtedly has sufficient financial capacity to perform the specific project when assessing the risk and contract value. If Energinet.dk on this basis finds the applicant unqualified, Energinet.dk can choose to exclude the applicant from the pre-qualification.
An applicant may rely on the capacities of other entities, regardless of the legal nature of the links which it has with them. The applicant must in that case prove to Energinet.dk that it will have at its disposal the resources necessary, for example, by producing an undertaking by those entities to that effect (signed declaration).
If suppliers have joint forces (i.e. joint ventures, consortia, ect.) the most resent audited annual report in Danish or English must be enclosed for each partitioning entity. If such information is not included, or is not fully sufficient, for one or more participant, the application will not necessarily be regarded as non-compliant, but any such failure to include this information may influence the pre-qualification evaluation process.
If more than 5 references are included in the pre-qualification Energinet.dk will only include the first 5 mentioned references in the evaluation of the pre-qualification process.
If one or more references are missing the requested information, and such cannot be requested as supplementary information, this may influence the prequalification evaluation process.
Energinet.dk reserves the right to contact the stated references. Furthermore Energinet.dk also reserve the right to include own references if the applicant has concluded similar assignments within the last three years for Energinet.dk.
An applicant may rely on the capacities of other entities, regardless of the legal nature of the links which it has with them. The applicant must in that case prove to Energinet.dk that it will have at its disposal the resources necessary, for example, by producing an undertaking by those entities to that effect (signed declaration).
If suppliers have joint forces (i.e. joint ventures, consortia, ect.) references must be enclosed for each partitioning entity. If such information is not included, or is not fully sufficient, for one or more participant, the application will not necessarily be regarded as non-compliant, but any such failure to include this information may influence the pre-qualification evaluation process.
Section IV: Procedure
Some candidates have already been selected (if appropriate under certain types of negotiated procedures): no
Notice on a buyer profile
Notice number in the OJEU: 2015/S 127-234196 of 4.7.2015
Section VI: Complementary information
https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET and must be written in Danish or English.
Requests received after the determined deadline will not be accepted.Energinet.dk reserves the right to obtain supplementing information from the applicant.
Energinet.dk will pre-qualify up to 5 applicants who are evaluated as most qualified for the specific tender. Only these applicants will be invited to submit a tender. The selection of 5 applicants will be based on the submitted references (to which extend the reference(s) are similar to the tender assignment). As a result the number of references will not be the determining factor alone but more importantly to which degree the specific forwarded reference are comparable and relevant to the tender assignment regarding the solution and scope.
Energinet.dk has joined Global Compact, and is using the 10 principles as a platform for working with CSR and Energinet.dk‘s Code of Conduct. Energinet.dk‘s CSR profile is visible at our homepage: www.energinet.dk. Applicants who Energinet.dk enters into contracts with are expected to act in accordance with Energinet.dk‘s Code of Conduct.
Klagenævnet for Udbud
Langelinie Alle 17
2100 København Ø
DENMARK
Internet address: http://www.klfu.dk